Budget
$215,000
Team Size
10 workers
Square Footage
7,800 sq ft
Progress
100%
Project Overview
View Project
Project Challenges
Restoring a heritage-listed building to meet current waterproofing standards
Replacing original corrugated iron with period-appropriate materials
Integrating modern guttering and drainage into a century-old structure
Adhering to a strict council-approved heritage conservation plan
Project Timeline
Heritage Assessment & Planning Approval
July 2025
Completed
Scaffold Erection & Site Preparation
August 2025
Completed
Existing Roof Removal & Structural Inspection
September 2025
Completed
Structural Repairs & New Sarking
October 2025
Completed
Period-Style Roof Sheet Installation
November 2025
Completed
Guttering, Flashings & Final Inspection
December 2025
Completed
Project Information
-
LocationSubiaco, WA
-
ClientCommercial Property Owner
-
Start DateAugust 2025
-
Expected CompletionDecember 2025