Budget
$1.15M
Team Size
26 workers
Square Footage
43,000 sq ft
Progress
100%
Project Overview
View Project
Project Challenges
Maintaining full venue operations throughout the restoration works
Working at significant heights across a complex multi-level roof structure
Coordinating access around a live events schedule with zero disruption tolerance
Managing large-scale waterproofing and coating application across four roof zones
Project Timeline
Condition Assessment & Scope Sign-Off
May 2025
Completed
Scaffold & Access Platform Installation
June 2025
Completed
Zone 1: North Hall Roof Restoration
August 2025
Completed
Zone 2: Main Auditorium Roof
October 2025
Completed
Zone 3: South Wing & Connector Roofs
December 2025
Completed
Guttering, Drainage & Final Client Handover
February 2026
Completed
Project Information
-
LocationPerth CBD, WA
-
ClientGovernment / Venue Operator
-
Start DateJune 2025
-
Expected CompletionFebruary 2026