Budget
$365,000
Team Size
14 workers
Square Footage
11,800 sq ft
Progress
90%
Project Overview
Project Challenges
Full roof replacement on an occupied 6-storey office building
Installing new insulation and vapour barrier to meet current energy codes
Coordinating roof penetrations for HVAC and mechanical systems
Maintaining a weatherproof staging environment to protect tenants throughout
Project Timeline
Existing Roof Strip & Waste Disposal
October 2025
Completed
Structural Deck Repairs
November 2025
Completed
Insulation & Vapour Barrier
December 2025
Completed
Standing Seam Metal Roof Installation
February 2026
Completed
HVAC Penetrations & Flashings
March 2026
Completed
Final Inspection & Client Handover
April 2026
In Progress
Project Information
-
LocationWest Perth, WA
-
ClientCorporate Client
-
Start DateOctober 2025
-
Expected CompletionApril 2026